C is twice as fast as a and b working together, and can complete the work 4 days earlier than a and b working together. if a takes 16 days to do the work alone, how many days would b alone take?

Question: c is twice as fast as a and b working together, and can complete the work 4 days earlier than a and b working together. if a takes 16 days to do the work alone, how many days would b alone take? 

Solution: Sure, I can help you with that.

Let's say the total work is represented by 16 units.

If A takes 16 days to do the work alone, then A can do 1 unit of work in 1 day.

Since C is twice as fast as A and B working together, then C can do 1 unit of work in half the time that A and B working together can do 1 unit of work.

Let's say the number of days it takes A and B working together to do 1 unit of work is x.

This means that C can do 1 unit of work in x/2 days.

We also know that C can complete the work 4 days earlier than A and B working together.

This means that the total number of days it takes C to complete the work is x/2 - 4.

Since the total work is represented by 16 units and C can do 1 unit of work in x/2 - 4 days, then C can complete the total work in (x/2 - 4)*16 = 8x - 64 days.

We are also given that c is twice as fast as A and B working together.

This means that the total number of days it takes A and B working together to complete the work is 8x - 64 / 2 = 4x - 32 days.

We are also given that if a takes 16 days to do the work alone, then A and B working together can finish the work in 14 days.

This means that 4x - 32 = 14

4x = 46

x = 11.5

Since x is the number of days it takes A and B working together to do 1 unit of work, then it takes A and B a total of 11.5 * 16 = 184 days to complete the total work.

Since A can do 1 unit of work in 1 day, then B can do 1/184 units of work in 1 day.

Therefore, it takes B a total of 184 days to complete the total work.

So the answer is 184

Post a Comment

Previous Post Next Post

Ads

Ad